Western Downs Battery
Stages 1–2: 540 MW / 1,080 MWh. Stage 3: 305 MW / 1,220 MWh.
- Identifier
- western-downs-battery
- Location
- Near Chinchilla, Western Downs, Queensland
- Developer / lead organisation
- Neoen
- Technology
- Battery storage
- Recorded status
- Construction / operating stages
Status evidence
The developer identifies stages 1 and 2 as operating and stage 3 as under construction. The combined capacity is not all operating.
Published milestones
Expected start of operation: Australian summer 2027/28, as announced on 10 December 2025. This is an estimate, not a confirmed completion date.
Procurement status
The developer provides an expression-of-interest channel for battery construction work. No specific open tender package, deadline or contract award was verified. An expression of interest does not guarantee work.
Potential relevance
Potential relevance (RRE inference): equipment, evidence, freight and qualified service capabilities may be relevant to projects of this type. This is not a confirmed work package or invitation.
Developer work-with-us information (not a tender)
Approvals, financing, procurement, construction and operation are separate stages. This profile does not independently verify all approvals, financing or site conditions. RRE does not represent the developer or guarantee opportunities.
Sources and checks
- Neoen — Battery
Source date: Not stated on page · Checked: 2026-10-08 - Neoen — December 2025 announcement
Source date: 2025-12-10 · Checked: 2026-10-08 - Neoen — Work with us
Source date: Not stated on page · Checked: 2026-10-08